Cascade completed a non-hazardous excavation and transportation and disposal project in Kearny, New Jersey, while navigating site access constraints and working near other contractors. The scope included removing a 5,000-square-foot concrete slab, excavating a 260-square-foot area to depths of 14 to 16 feet, clearing vegetation, and performing test pits beneath the slab. Despite a brief shutdown while awaiting client sampling results, the three-week project was completed ahead of schedule and within the original budget.
Precision Excavation in a Constrained Site: Cascade navigated access challenges and nearby contractor activity while safely completing concrete removal, test pitting, vegetation clearing, and excavation to depths of 14 to 16 feet.
Ahead of Schedule and Within Budget: Despite a temporary shutdown while awaiting client sampling results, Cascade completed the project ahead of schedule and within the original budget.
See how Cascade navigated site constraints to successfully execute this non-hazardous excavation project.