Following confirmation that remedial goals had been met, Cascade decommissioned and removed an Air Sparge and Soil Vapor Extraction system while addressing a TCE contamination hotspot and restoring the site. The work included decommissioning 47 wells, removing 33 concrete vaults, backfilling void spaces, providing transportation and disposal services, and completing site restoration. Because the property remained in use for RV storage, Cascade coordinated access and workspace around ongoing operations. The project was completed in 15 days, ahead of schedule and under budget, allowing the property sale to proceed without delay.
Decommissioning Without Operational Disruption: Cascade coordinated system removal, TCE hotspot excavation, and site restoration while keeping the property fully operational throughout the project.
Ahead of Schedule and Under Budget: Cascade completed the project within 15 days, ahead of schedule and under budget, enabling the property owner to move forward with the sale without delays.
Learn how Cascade coordinated system decommissioning, contamination removal, and site restoration to prepare the property for its next phase.